Severn Tunnel reopens as electrification is completed

26 October 2016/Categories: CILT, Industry News, Rail, Transport Planning


The Severn Tunnel reopened to rail passengers on Saturday, 22nd October following the completion of six weeks of upgrade work to prepare it for electrification, which will result in more seats and faster, more reliable journeys for passengers.

Network Rail’s ‘orange army’ worked day and night to install over eight miles of conductor rail which will eventually power a new fleet of electric trains through the 130 year-old tunnel. An extensive amount of work to prepare neighbouring Patchway Tunnels was also completed during the closure, which took place between 12th September and 21st October as part of Network Rail’s Railway Upgrade Plan to provide a bigger and better railway for passengers.

Andy Thomas, Network Rail Wales route managing director, said: “We are delighted to have delivered this vital milestone in the project to electrify the South Wales Mainline as part of our Railway Upgrade Plan to give passengers a bigger and better railway. We would like to thank passengers for their patience – without this six week closure it would have taken engineers up to five years to complete this vital upgrade, delaying electrification to South Wales.

“Electrification of the South Wales Mainline will transform the railway, bringing significant long-term benefits for passengers including faster, more frequent trains as well as a boost to economic growth for towns and cities across South Wales thanks to better connectivity to and from London.”

Dan Tipper, project director at Network Rail Wales, said: “It has been a phenomenal team effort, involving over 250 engineers and close working with our principal contractors ABC Electrification and Babcock as well as numerous suppliers, designers and sub-contractors including Amco, Keltbray and Arup, to deliver this essential stage of the electrification project. I would like to thank every single member of the team that has worked on this iconic project for their hard work and dedication to deliver this upgrade successfully and on time.”

During the tunnel closure GWR high-speed train services were diverted between Swindon and Newport which increased journey times by approximately 35 minutes.

GWR development manager for Wales, Mark Youngman, said: "This work is a vital part of the modernisation of the railway between South Wales and London; which, once complete, will enable us to deliver more frequent services, more seats, and to reduce journey times.

“We would like to thank all of our passengers for their patience during the last six weeks. We worked closely with Network Rail and local government to make sure we kept customers on trains wherever possible and provided the quickest, most convenient journey to their destination, minimising disruption as best we could.”

John Skentelbery, tunnels operations director for ABC Electrification, said: “This part of the electrification scheme was a huge challenge and we have all worked extremely hard to complete the work safely and on time. I am very proud of this team and what we have achieved in the last six weeks.”

Print

Number of views (1837)

Tags:

Theme picker

Registered Office:

Earlstrees Court, Earlstrees Road, Corby
Northants, NN17 4AX
Main Switchboard: 01536 740100

Company Registration Number: 2629347 
(A Company Limited by Guarantee)
Charity Registration Number: 1004963

© The Chartered Institute of Logistics and Transport