Britain's biggest motorway service chain is having to build solar farms in order to power its electric vehicle charging hubs due to a lack of adequate grid connections.
Analysis by the Department for Transport found that, in 2024, only 105 of motorway service areas in England had the power capacity they would need to meet rapid charge point demand for 2035, with around half needing to increase their capacity by between two and ten times.
Moto, which runs 70 service stations across the UK, is planning to build more than a dozen new solar sites, with permissions currently acquired for four locations - including a 7-megawatt solar array at Wetherby.

Moto’s chief executive, Ken McMeikan, said that he was frustrated by the speed at which they are getting sufficient power to sites, especially with a growing demand because of the ongoing transition to electric.
As motorway service stations are often far away from built up areas, connecting service areas to the grid can involve laying cables across miles of farmland, previously forcing Moto to drill underneath eight-lane carriageways to hook up its chargers to distant substations.
Moto revealed that it can take up to four years to get the power to each site, making it impossible to be ahead of demand. The firm is attempting to plan ahead by buying or renting farmland around their service stations in order to install solar farms backed up by battery storage facilities. The operator estimates that in just four years, their service areas alone will be dispensing power equivalent to half the output of an average nuclear power station.
Moto is currently the leading provider of ultra-rapid EV charging points on the motorway network, with its other solar farm projects including a 7.15-megawatt solar development at Donington Park services on the M1 and a 4-megawatt site at Stirling.